Newton Marsh

BACK TO PROJECTS

Project Size: 4.6MW
Turbine: 2 x Enercon E70
Dimensions: Overall height to tip 105m
Status: Constructed

Location:
Lincolnshire: situated at Anglian Water Services’ Newton Marsh Sewage Treatment Works, approximately 2.2 km north-east of Tetney.

Summary:
The wind turbines are capable of producing up to 2.3MW of green power each for use by Anglian Water Services to power the Works, with surplus electricity being fed into the local grid.

The planning application was submitted in December 2007 and subsequently refused in 2008.TCI Renewables submitted an appeal which was allowed in 2009. Work commenced on site in 2012 and was completed in early 2014.

Public Consultation:
Public information programmes were held in 2007 to advise the local community and stakeholders of the development proposals.